Project Description

Client: ISG
Project Name: HSBC Edinburgh
Project Location: HSBC, 76 Hanover Street, Edinburgh, EH2 1EL
Contract Length: 14 Weeks
Services: Mechanical & Electrical

Complete install of mechanical & electrical services to ground floor of branch. Works carried out as follows:

Mechanical – Strip out of existing ventilation and AC services to the ground floor. Installation of new MVHR & FCU units throughout ground floor along with all associated ductwork and grilles. Installation of new external AC condensers and internal AC units to ground floor along with all associated pipework.

Installation of new domestic water supplies to water and coffee machines.

Installation of new over door heater with associated controls.

Electrical – Installation of new distribution boards with integral metering and surge protection. Installation of primary and secondary containment for lighting, small power, data, security, and AV services.

Installation of new LED lighting throughout ground floor including emergency lighting and lighting controls in meeting rooms incorporating scene setting plates for final users to control lighting.

Installation of small power to all items of furniture and mechanical items.

Commissioning and testing of all of the above items.